Question 1
The AC and DC disconnects for a rooftop inverter have been opened and locked out. Its display is dark, and the manufacturer's capacitor-discharge time has elapsed. Before a qualified electrician treats the inverter terminals as de-energized, what evidence is still needed?
Show answer & explanation
Correct answer: D - Absence-of-voltage tests at the work points, with the tester proved before and after.